Energy supply: Operation of energy supply networks - Authorization

Source: Zuständigkeitsfinder Schleswig-Holstein (Linie6Plus)

Service Description

Anyone wishing to operate an energy supply network requires a permit.

If you intend to operate an energy supply network, you require approval from the competent authority under state law.

Prerequisites: You have the

  • the personnel, technical and economic capacity and
  • reliability,

to ensure long-term grid operation in accordance with the statutory regulations.


Who should I contact?

To the Ministry for Energy Transition, Climate Protection, Environment and Nature of the State of Schleswig-Holstein (MEKUN).

Which documents are required?
  • Information on the network (acquisition, construction of a new network, investments, network capacity, presentation of the network),
  • Information on the customers whose supply is to be included,
  • Information on the gas/electricity purchases of the customers,
  • Proof of the legal form of the company (extract from the commercial register, articles of association),
  • Documents on personnel and technical capacity (organization chart with number of employees and their qualifications), technical equipment (see VDN guideline S-1000 or DVGW worksheet G 1000), submission of contracts with subcontractors,
  • Submission of a profit and loss forecast (investments and depreciation, capital and financial plan, operating expenses, profit and loss account),
  • Documents on economic performance (proof of equity, shareholdings in the company, most recent profit and loss account).
What are the fees?

The fees are calculated on a time and material basis. Detailed information can be obtained from MEKUN.

https://www.schleswig-holstein.de/DE/Landesregierung/V/v_node.html

What deadlines do I have to pay attention to?

None

Legal basis
Applications / forms

Informal application.

Author

The text was automatically translated based on the German content.

Teaser

Anyone wishing to operate an energy supply network requires a permit.

Who should I contact?

To the Ministry for Energy Transition, Climate Protection, Environment and Nature of the State of Schleswig-Holstein (MEKUN).

Which documents are required?

  • Information on the network (acquisition, construction of a new network, investments, network capacity, presentation of the network),
  • Information on the customers whose supply is to be included,
  • Information on the gas/electricity purchases of the customers,
  • Proof of the legal form of the company (extract from the commercial register, articles of association),
  • Documents on personnel and technical capacity (organization chart with number of employees and their qualifications), technical equipment (see VDN guideline S-1000 or DVGW worksheet G 1000), submission of contracts with subcontractors,
  • Submission of a profit and loss forecast (investments and depreciation, capital and financial plan, operating expenses, profit and loss account),
  • Documents on economic performance (proof of equity, shareholdings in the company, most recent profit and loss account).

What are the fees?

The fees are calculated on a time and material basis. Detailed information can be obtained from MEKUN.

https://www.schleswig-holstein.de/DE/Landesregierung/V/v_node.html

What deadlines do I have to pay attention to?

None