Notify change of operator of a system for handling substances hazardous to water (AwSV system, except heating oil consumer system and JGS system)

Source: Zuständigkeitsfinder Schleswig-Holstein (Linie6PLus)

Service Description

If you take over a system for handling substances hazardous to water, this change of operator must be reported to the competent authority.

When taking over an existing installation for handling substances hazardous to water, you as the new operator of the installation are obliged to notify the competent authority of this change of operator without delay. With the notification, you provide the competent authority with information on the previous and new operators, the owner and the takeover of the installation. The obligation to notify does not apply to heating oil consumer installations.


Process flow
  • You fill out the forms required for the notification and send them to the lower water authority by post or email or use the online service.
  • The authority will check your documents for completeness and request any missing information or documents.
  • In addition, the content requirements are checked, which may also result in additional claims.
  • If there are no objections, your application data will be entered into the authority's specialist procedure.
Competent authority

In Schleswig-Holstein, the lower water authorities of the districts or independent cities are responsible.

Requirements

The prerequisite is a system subject to mandatory testing in which substances hazardous to water are handled, with the exception of heating oil consumer systems.

Which documents are required?

Completed notification form

What are the fees?

Fee: 25,00 - 1000,00 EUR
Payment in advance: No
The notification may be subject to a fee if, for example, a notice has to be issued.

What deadlines do I have to pay attention to?

The change of operator must be reported immediately in writing or online.

Processing duration

Processing time: 2 - 4 Weeks

Legal basis
What else should I know?
Author

The text was automatically translated based on the German content.

Technically approved by

Ministry for Energy Transition, Climate Protection, Environment and Nature of the State of Schleswig-Holstein

Professionally released on

05.07.2023

Teaser

If you take over a system for handling substances hazardous to water, this change of operator must be reported to the competent authority.

Process flow

  • You fill out the forms required for the notification and send them to the lower water authority by post or email or use the online service.
  • The authority will check your documents for completeness and request any missing information or documents.
  • In addition, the content requirements are checked, which may also result in additional claims.
  • If there are no objections, your application data will be entered into the authority's specialist procedure.

Competent authority

In Schleswig-Holstein, the lower water authorities of the districts or independent cities are responsible.

Requirements

The prerequisite is a system subject to mandatory testing in which substances hazardous to water are handled, with the exception of heating oil consumer systems.

Which documents are required?

Completed notification form

What are the fees?

Fee: 25,00 - 1000,00 EUR
Payment in advance: No
The notification may be subject to a fee if, for example, a notice has to be issued.

What deadlines do I have to pay attention to?

The change of operator must be reported immediately in writing or online.

Processing duration

Processing time: 2 - 4 Weeks

Legal basis

What else should I know?

Author

The text was automatically translated based on the German content.

Technically approved by

Ministry for Energy Transition, Climate Protection, Environment and Nature of the State of Schleswig-Holstein

Professionally released on

05.07.2023

Further information and offers