If you wish to make significant changes to or in surface waters or an existing facility or construct a facility, you must apply for a permit from the responsible lower water authority.

If you wish to construct a facility or make significant changes to an existing facility in, above, below, over or on surface waters, you can apply for a permit from the water authority. Installations can be: dams, bridges, crossings, culverts, watercourse crossings with supply/supply lines, construction measures on watercourses, pipeline routes parallel to watercourses, bank reinforcements and property enclosures, footbridges, embankments or land filling/removal.

Installations can be

  • Dams,
  • bridge,
  • crossing,
  • culvert,
  • watercourse crossing with supply/disposal line,
  • Construction work on the watercourse,
  • pipeline route parallel to the watercourse,
  • Bank reinforcements and property enclosures,
  • footbridge,
  • management or land filling/removal.

Process flow

You can apply informally for approval of installations on surface waters.

- The competent authority will review your application

- You will receive feedback on your application

Competent authority

Lower water authority (depending on location)

Which documents are required?

- Declaration of consent from the landowner, if applicable

- Declaration of consent from the water and soil association, if applicable

What are the fees?

The application is free of charge. There may be a fee for the administrative procedure, which is charged upon completion of the approval process. In most cases, the fee for companies and private individuals is €50.

Further information can be found at the link provided (State Ordinance on Administrative Fees, Annex "General Fee Schedule" Section 24.1).

Legal basis
Appeal

Contradiction

Author

The text was automatically translated based on the German content.

Teaser

If you wish to make significant changes to or in surface waters or an existing facility or construct a facility, you must apply for a permit from the responsible lower water authority.

Process flow

You can apply informally for approval of installations on surface waters.

- The competent authority will review your application

- You will receive feedback on your application

Competent authority

Lower water authority (depending on location)

Which documents are required?

- Declaration of consent from the landowner, if applicable

- Declaration of consent from the water and soil association, if applicable

What are the fees?

The application is free of charge. There may be a fee for the administrative procedure, which is charged upon completion of the approval process. In most cases, the fee for companies and private individuals is €50.

Further information can be found at the link provided (State Ordinance on Administrative Fees, Annex "General Fee Schedule" Section 24.1).

Legal basis

Appeal

Contradiction

Author

The text was automatically translated based on the German content.

Further information and offers