Show construction, significant modification or decommissioning of a slurry, liquid manure and silage slurry plant (JGS plant)

Source: Zuständigkeitsfinder Schleswig-Holstein (Linie6PLus)

Service Description

If you have a

  • silage leachate storage facility with a volume of more than 25 cubic meters,
  • any other JGS facility with a total volume of more than 500 cubic meters, or
  • a facility for the storage of solid manure or silage with a volume of more than 1,000 cubic meters, you must notify the competent authority.

Process flow
  • You fill out the forms required for the notification and send them to the lower water authority by post or email or use the online service for the application.
  • In either case, the authority will check your documents for completeness and request any missing information or documents.
  • In addition, the content requirements will be checked, which may also result in additional claims.
  • If there are no objections, your application data will be entered into the authority's specialist procedure.
Competent authority

In Schleswig-Holstein, the lower water authorities of the districts or independent cities are responsible.

Requirements

You provide the necessary documents to prove that your system complies with the requirements of the Ordinance on Systems for Handling Substances Hazardous to Water (AwSV).

Which documents are required?
  • Completed notification form
  • Detailed documents describing the project (site plan, drawings, certificates, descriptions)
  • Expert opinion, if applicable
What are the fees?

Fee: 25,00 - 1000,00 EUR
Payment in advance: No

What deadlines do I have to pay attention to?

You must notify the competent authority in writing or online at least six weeks in advance.

Processing duration

Processing time: 2 - 4 Weeks

Legal basis
Author

The text was automatically translated based on the German content.

Technically approved by

Ministry for Energy Transition, Climate Protection, Environment and Nature of the State of Schleswig-Holstein

Professionally released on

05.07.2023

Process flow

  • You fill out the forms required for the notification and send them to the lower water authority by post or email or use the online service for the application.
  • In either case, the authority will check your documents for completeness and request any missing information or documents.
  • In addition, the content requirements will be checked, which may also result in additional claims.
  • If there are no objections, your application data will be entered into the authority's specialist procedure.

Competent authority

In Schleswig-Holstein, the lower water authorities of the districts or independent cities are responsible.

Requirements

You provide the necessary documents to prove that your system complies with the requirements of the Ordinance on Systems for Handling Substances Hazardous to Water (AwSV).

Which documents are required?

  • Completed notification form
  • Detailed documents describing the project (site plan, drawings, certificates, descriptions)
  • Expert opinion, if applicable

What are the fees?

Fee: 25,00 - 1000,00 EUR
Payment in advance: No

What deadlines do I have to pay attention to?

You must notify the competent authority in writing or online at least six weeks in advance.

Processing duration

Processing time: 2 - 4 Weeks

Legal basis

Author

The text was automatically translated based on the German content.

Technically approved by

Ministry for Energy Transition, Climate Protection, Environment and Nature of the State of Schleswig-Holstein

Professionally released on

05.07.2023

Further information and offers