responsibility finder
Schleswig-Holstein

Roadworks in road traffic: Roadworks layout

Source: Zuständigkeitsfinder Schleswig-Holstein (Linie6PLus)

Service Description

Work sites that have an impact on road traffic (e.g. excavations in the road, road construction, work in the side area, erection of scaffolding) must be secured.

Before starting work, the contractor must obtain instructions from the competent authority on how the work site is to be cordoned off and marked and how traffic is to be restricted, regulated and routed.

Requirements:
The traffic measures required to secure the work site must always be examined on a case-by-case basis. The contractor and the road traffic authority can refer to the guidelines for traffic safety at road works (RSA).

Procedure:
The contractor must already check which traffic safety measures are necessary and appropriate during the planning phase of the work site based on the local conditions. Following this, a written application must be submitted to the traffic authority for the traffic safety measures to be ordered. The competent authority examines the application and the documents submitted and consults the authorities to be involved (including the police and road construction authorities). If necessary, a site inspection is carried out with all parties involved in order to coordinate the necessary measures on site. The necessary measures are then ordered to be carried out by the contractor.


Who should I contact?

To the road traffic authorities in the:

  • Districts and independent towns,
  • towns and municipalities with more than 20,000 inhabitants,
  • independent towns and municipalities with up to 20,000 inhabitants,
  • public authorities, if the construction site extends exclusively to their own district

or to the Schleswig-Holstein Road Construction and Transport Authority.

Which documents are required?
  • Written application,
  • Traffic sign plan (either standard plan of the RSA or individual),
  • Detour plan if necessary.

Detailed information can be obtained from the responsible office.

What are the fees?

Fees of between 10.20 euros and 767.00 euros apply. More detailed information can be obtained from the responsible office.

What deadlines do I have to pay attention to?

The application must be submitted at least two weeks before the start of construction work.
Extensive construction work requires a much longer lead time.

Legal basis
  • §§ Sections 44, 45 of the Road Traffic Regulations (StVO),
  • Fee schedule for road traffic measures (GebOSt), fee no. 261.
Author

The text was automatically translated based on the German content.

Who should I contact?

To the road traffic authorities in the:

  • Districts and independent towns,
  • towns and municipalities with more than 20,000 inhabitants,
  • independent towns and municipalities with up to 20,000 inhabitants,
  • public authorities, if the construction site extends exclusively to their own district

or to the Schleswig-Holstein Road Construction and Transport Authority.

Which documents are required?

  • Written application,
  • Traffic sign plan (either standard plan of the RSA or individual),
  • Detour plan if necessary.

Detailed information can be obtained from the responsible office.

What are the fees?

Fees of between 10.20 euros and 767.00 euros apply. More detailed information can be obtained from the responsible office.

What deadlines do I have to pay attention to?

The application must be submitted at least two weeks before the start of construction work.
Extensive construction work requires a much longer lead time.

Legal basis

  • §§ Sections 44, 45 of the Road Traffic Regulations (StVO),
  • Fee schedule for road traffic measures (GebOSt), fee no. 261.

Author

The text was automatically translated based on the German content.

Further information and offers